The 3D model is an illustration built from public record figures. It is not an engineering survey. This page lists where every figure comes from and marks each one as documented, measured, an estimate or an assumption.
Record documents
Document
Case / date
Used for
Supplemental Direct Testimony of Trey M. Rydel, p. 4
SCC PUR-2025-00056, filing 380967, May 16, 2025
Route 3A structure heights: about 110 to 180 ft, average about 154 ft, preliminary, not including foundation reveal. Structure families by right-of-way width.
Application Appendix Vol. 1, Attachments II.B.3.vi to viii (typical structure drawings), PDF pp. 147-161
PUR-2025-00056, filing 380957, Mar. 28, 2025
Shape of each structure type: pole spacing, arm heights and lengths; minimum conductor-to-ground clearance 27.5 ft (500 kV) and 22.5 ft (230 kV).
Motion for leave to file supplemental testimony
PUR-2025-00056, filing 380965, May 16, 2025
Route 3A "requires several additional two-pole angle structures".
SCC Staff testimony of Jay-Ar Llamido, Part B
PUR-2025-00056, filing 385307, Nov. 12, 2025
Route 3A: 74 structures by type (citing Dominion response to Staff Interrogatory 1-25). Routes 1 to 5: totals 83, 81, 74, 74, 88 and heights of about 110 to 185 ft, average about 156 ft.
Hearing transcript, Rosenberg, Tr. 2390-91, 2468
PUR-2025-00056
Route 1F: not proposed for approval; number of structures "Not sure at this point".
Dominion/ERM map sheet "Golden-Mars Route 3A" with structure locations
Republished by the Piedmont Environmental Council (pecva.org)
Positions of structures S1 to S5 behind Oatlands Grove Pl.
The record gives one range for all of Route 3A: about 110 to 180 ft, average about 154 ft, "based on preliminary conceptual design, not including foundation reveal, and subject to change" (Rydel supplemental direct, p. 4). It gives no height for any single structure.
The model draws every structure at one height, 165 ft by default, chosen by United Loudoun inside the record range. The Adjust tab has a slider from 110 to 180 ft. For reference, Attachment II.B.3.viii lists 160 to 175 ft (average 165 ft) for the 2-pole type on Route 3.
The heights in the record do not include foundation reveal (the part of the foundation above the ground), which may add to the height of a structure above ground. The model does not add it.
Wires are drawn as a parabola with mid-span sag equal to a share of the span length (slider 1 to 6 percent). Sag is not in the record. One wire is drawn per phase; the record describes a triple bundle at 500 kV and a twin bundle at 230 kV.
The table in the Adjust tab is computed from the height and sag settings and the LiDAR ground. It is compared with the record minimum conductor-to-ground clearance of 27.5 ft (500 kV) and 22.5 ft (230 kV) at maximum operating temperature (Attachments II.B.3.vi to viii).
A figure below the minimum means the model's single height and sag assumptions do not hold on that span. It is not a finding about Dominion's design. This happens on the longest span, #20 to #21 (1,213 ft).
In the After view every LiDAR tree whose top falls within 150 ft centered on the centerline is removed, and the ground is painted as meadow. 150 ft is the widest right-of-way in the record ("primarily varying between 100 and 150 feet wide"). Dominion's own right-of-way polygon measures 100 ft across this area; it can be switched on under Layers. The clearing shown is therefore wider than Dominion's polygon here.
Trees are measured from LiDAR flown in 2022. The default adds 3 ft to every tree 5 m or taller, a general estimate for mature canopy; it is not measured. The slider runs from 0 (exactly as measured) to 6 ft.
Positions and heights are LiDAR tree tops (2022): 95,276 trees in the model area after removing points that were really wires, towers or poles. Crown width comes from the canopy surface, widened toward the nearest neighbor (up to 9 m) so that closed canopy reads closed. Crown shapes are drawn, not measured. Trees that read green in the leaf-off 2026 imagery are drawn as evergreens; this is a visual reading, not a species survey.
Summer and Winter use the same trees and heights. In Winter, broadleaf trees are a generic branch frame. Dominion's photo simulations are almost all summer: 25 of 32 photos in the 2025 set and 22 of 22 in 2024.
In an on-the-ground view, trees whose crown would cover the camera itself are not drawn.
County building footprints with heights from LiDAR roof returns. 218 buildings had too few returns (most were built after the 2022 flight) and use assumed heights: sheds under 40 m2 at 2.5 m eave and 3.5 m ridge, others at 6 m and 9 m. Roof shapes are generic, except at the two schools (next entry).
Rock Ridge High School and Rosa Lee Carter Elementary School measured#
Each school is one County building footprint. Its roof heights were mapped from the 2022 LiDAR returns at 1 m and split into flat-roofed blocks, each drawn at its measured height above the ground beneath it (both sites slope) (Rock Ridge: classroom wings about 29 ft, central blocks about 36 ft, other parts 15 to 26 ft; Rosa Lee Carter: about 14 ft, with a taller block of about 24 ft). Open courtyards inside the footprints are left open. Rooftop equipment that stands clear of the roof is drawn as boxes at its measured position and height. Where the 2022 data did not classify a roof as building, the surface height from the same flight is used.
Entrances are placed one by one: Rock Ridge's front canopy and Rosa Lee Carter's main portico at the positions and heights the LiDAR shows; Rosa Lee Carter's smaller east portico from the 2026 imagery. Rock Ridge's two covered walkways along the front, either side of the entrance canopy, are drawn where the LiDAR shows their roofs (about 11 ft up, 67 and 72 ft long, about 20 ft deep). Which way each faces, and roof colors (white at Rock Ridge, dark at Rosa Lee Carter), follow the County's oblique aerial images.
Illustrative, not measured: brick, stone bands, window pattern, canopy and portico shapes and widths, drawn after photos of each school. The 2022 tree finder read some unclassified roof returns at Rock Ridge as trees; trees standing on the school roofs are not drawn.
A telecommunications monopole stands by the Rock Ridge stadium: 142 ft, the height in its commission permit (CMPT-2021-0001), at the position of a narrow spike in the 2022 LiDAR that reads 140 ft at the top. The antenna platform is illustrative.
The address search measures from the County address point to the Route 3A centerline. It is not the distance from the house wall or the lot line, so it can differ from distances in the record (Staff testimony lists the three closest residences at 112, 97 and 102 ft).
Eye height 5.5 ft. Each view was picked and checked by hand and faces a Route 3A structure; the caption names the nearest one. The two Broad Run crossing views look along the line.
View
To the centerline
Where
Oatlands Grove Pl back yard
101 ft
Back yard of a house on Oatlands Grove Pl, on the lawn behind the house
Oatlands Grove Pl cul-de-sac
245 ft
Center of the Oatlands Grove Pl cul-de-sac
Glenorchy Ct
114 ft
Beside a house on Glenorchy Ct, the house closest to the line in this stretch
Barnstead Dr
207 ft
Beside a house on Barnstead Dr
Rock Ridge HS
1052 ft
Outside the west side of Rock Ridge High School, facing the line
Rosa Lee Carter ES
375 ft
West end of the Rosa Lee Carter Elementary School bus loop, facing the line
Broad Run crossing (north)
0 ft
Broad Run stream valley where the line crosses the stream
Broad Run crossing (south)
1 ft
Broad Run stream valley where the line crosses the stream
Line traces are the County Major Power Lines layer. Towers were found in the 2022 LiDAR as isolated peaks at least 18 m tall within 10 m of a line: 246 towers in the model area, typically about 100 ft tall. Positions and heights are measured. Tower shape, arm layout and wire sag are generic and not Dominion data.
Routes 1, 2, 3, 4 and 5 and their towers estimate#
Route lines: point lists compiled by Loudoun Valley Estates from Dominion's published route files and FOIA files. Route 3A is drawn from Dominion's own centerline file instead.
Routes 1, 2, 3, 4 and 5 structures: ASSUMED positions. The record gives only each route's total count (83, 81, 74, 74 and 88) and heights of about 110-185 ft, average about 156 ft. Placed by the same rule as Route 3A: one at every point of the route in the case-folder routes file, plus one at the middle of any stretch longer than 400 m. All drawn as monopoles (suspension where the line turns less than 3 degrees, double dead-end otherwise) at 165 ft, the same height as Route 3A in this model (estimate; the record has no per-structure heights). Rule totals for the whole routes: 1: 73, 2: 70, 3: 65, 4: 67, 5: 78.
Record totals: Route 1: 83, Route 2: 81, Route 3: 74, Route 4: 74, Route 5: 88. The rule places fewer towers than the record, not more.
Route 1F: centerline from the Dominion file sent to VDOT on Jan. 12, 2026, obtained by Loudoun Valley Estates HOA through a VDOT FOIA request. Dominion did not propose it for approval (Rosenberg, Tr. 2468) and gave no structure count ("Not sure at this point", Tr. 2390) or heights. Towers placed by the same rule (85 for the whole route) and drawn at 165 ft, the same height as the other routes in this model, as an estimate.
Dominion's existing substation where the routes end, east of Carters School Rd. It was built after the 2022 LiDAR flight, so nothing at the site is measured from it; the 2022 trees that stood there are not drawn.
From the 2026 VBMP imagery: the fence line around the gravel yard (about 11 acres), the two large white-roofed halls, three smaller buildings, the line of tall poles along the north edge, and where equipment stands in the yard.
Illustrative, after photos taken from the public roadside on June 21, 2026: the gantries, bus, breakers and insulators and their arrangement, the chain-link fence (8 ft) and the dark steel line poles.
Heights are estimates: yard equipment and the two halls up to 50 ft, the maximum height Dominion gave for an expansion at Mars (Dominion's answer quoted in the County's testimony, filing 384575); line poles 100 ft, the typical measured height of the existing 230 kV towers in the model area; smaller buildings 15 ft.
Read from Attachment II.A.6, "Right-of-Way Subject to New and Existing Easements": the supplemental maps in filing 380966 (May 16, 2025, map Pages 3 to 5) and the original maps in filing 380957 (Mar. 28, 2025) as a check. The maps were placed on the model by matching their aerial images to the 2026 imagery, and the band was measured across each route every 10 m.
Drawn as dashed edge lines in each route's color, shown when the route is on: 100 ft where the maps show the 100 ft band, which is nearly everywhere in the model area; 150 ft where the maps mark the width as variable ("100-150 feet"), the upper end, an estimate. Stretches that share or cross an existing Dominion right-of-way (crosshatched on the maps, no new width given) are not drawn.
Route 1F is not on the application maps; its right-of-way is drawn at 150 ft, an estimate. Route 3A keeps Dominion's own right-of-way polygon and the 150 ft clearing.
Laid out from the approved site plan EPLAN-2023-0105 (sheet C-301) at its stated scale and fitted to the two buildings standing in the 2026 imagery. Buildings C, D and E are planned, not built. Wall panels, rooftop units and generator boxes are illustrative; unit sizes are estimates. The site plan lists 115 generators.
Item
Height
Basis
Building A
72 ft
documented
document: 72 ft to parapet, 2-story (EPLAN-2023-0105, sheets C-103 and C-303); position as built (2026 imagery)
Building B
72 ft
documented
document: 72 ft to parapet, 2-story (EPLAN-2023-0105, C-103, C-303); position as built (2026 imagery; moved by EPLAN-2023-0129)
Building C
100 ft
estimate
estimate: 3-story per EPLAN-2023-0129 approval (10/24/2025); 100 ft = zoning maximum with added setbacks (Zoning Ord. 4-606(B)); footprint from EPLAN-2023-0105 sheet C-301 (later revised, revision not in hand)
Building D
100 ft
estimate
estimate: as Building C
Building E
22 ft
documented
document: 22 ft to parapet (EPLAN-2023-0105, PDF p17); kept as full build-out although EPLAN-2023-0129 removed one smaller building
Northwoods Substation (Dominion and NOVEC)
30 ft
estimate
fence traced from the 2026 imagery (built); equipment height estimate: bus and switch structures up to about 23 ft dimensioned on the S9-04 Dominion elevations, 30 ft used (upper end); line masts scale to 79 ft on S9-04, not placed (positions not dimensioned)
The open land at Moorefield Station (Claude Moore Charitable Foundation land, rezoning ZMAP-2001-0003, zoned PD-TRC) is shown as it could look once built out. Shown with the "Moorefield build-out" switch under Layers; on when the page opens. Trees under the buildings and planned roads are hidden while it is on.
Planned buildings (156): outlines, story counts and uses read off the two approved Final Development Plans, FIDP-2018-0001 (Parcels C, D and E2, approved April 2019) and FIDP-2022-0002 Southmoore (approved September 2022: 2,120 apartments and 21,000 sq ft of retail in Blocks D-6, E2, E8, E13, E19, E22 and E24). The plans call their layouts illustrative; where a block shows options, option 1 is drawn. The sheets were placed on the model by matching their road and lot lines to the County road edges and parcels, or from a road intersection where the match was weak. Heights are estimates from the story counts (11 ft per residential or garage story, 14 ft per office or retail story, plus 4 ft parapet), never above the plan's stated maximum.
Loudoun County Pkwy frontage, first phase (20 buildings): FIDP-2018-0001 shows this land in two phases. Its ultimate phase (sheets 7 and 8) has offices of 3 to 9 stories, an 8-story hotel and parking garages of 9 to 10 levels, up to 100 ft; no site plan has been filed for them, and the developer's September 2026 exhibits mark the land as future commercial. Its first phase (sheet 6) gives Block D1, beside Claude Moore Dr west of the regional pond, eight one-story retail and restaurant pads with surface parking; those are drawn. For Blocks D2, D3, D4 and the D6 offices the plan gives no first phase, so one-story retail is drawn on the plan's office footprints and the garage sites as surface parking; these are estimates. One-story height: 14 ft plus 4 ft parapet (18 ft). The block north of Massie St east of the Midmoore Dr extension is labeled "Future mixed use / interim recreation use" on sheet 8 and is shown open, with no buildings.
Blocks with no building plan yet (40 buildings): the remaining blocks east of Claude Moore Dr toward the Metro station and the open block north of the planned Massie St. Drawn at the zoning maximum height (Inner Core 175 ft, Outer Core 125 ft, Transit Design Supportive Area 100 ft; FIDP-2022-0002 sheet 2, note 20) as perimeter buildings with a garage core. Footprints are illustrative. The 175 ft Transit District lies north of Metro Center Dr and the 125 ft Midtown District south of it, as on the developer's district map (moorefieldmetro.com, May 2025), which gives the two districts about 140 acres with potential for about 2,500 more homes and over 6 million sq ft of commercial space. Filling every such block to the maximum height gives more floor area than the rezoning allows in total, so this part overstates the build-out.
Built after the 2022 LiDAR: Aventon Moorefield (Block E8, 425 units, STPL-2023-0013), outline traced from the 2026 imagery, 76 ft to the top of the roof scaled off its building elevations. Under construction: a convenience store, fuel canopy over 8 dispensers and car wash at 22644 Amendola Ter (building, mechanical and sign permits 2025-2026); sizes, heights and positions within the lot are assumed.
Look: facades (windows, shop fronts, brick and light colors), the streets between blocks, 4 m sidewalks, courtyards, parking lots and young street trees every 9 m are illustrative, in the style of nearby mid-rise mixed-use centers; none of it comes from a plan.
Planned roads: Massie St and the Midmoore Dr extension to Loudoun County Pkwy (EPLAN-2024-0113, approved 2024; VESMP-2026-000112 in review), drawn as flat roadways.
Moorefield Station is approved for up to 6,000 homes and 9,750,000 sq ft of non-residential space (ZMAP-2001-0003 as amended); after FIDP-2022-0002, 1,552 homes and 6,928,000 sq ft remained to be planned (staff report, Sept. 1, 2022).
Distance from each route (centre line to the nearest building edge, and building centres within each band). Planned homes are the block maximums of FIDP-2022-0002 for blocks with a building in the band; tower positions on Routes 1-5 and 1F are placed by rule.
Route
Nearest build-out building
Within 500 ft
Within 1,000 ft
Within 1/2 mile
Route 1
33 ft
15 buildings, tallest 22 ft
117 buildings, tallest 48 ft, planned homes in blocks D6: 201
193 buildings, tallest 175 ft, planned homes in blocks D6/E13/E2: 854
Route 1F
33 ft
15 buildings, tallest 22 ft
117 buildings, tallest 48 ft, planned homes in blocks D6: 201
193 buildings, tallest 175 ft, planned homes in blocks D6/E13/E2: 854
Route 5
0 ft
15 buildings, tallest 22 ft
117 buildings, tallest 48 ft, planned homes in blocks D6: 201
193 buildings, tallest 175 ft, planned homes in blocks D6/E13/E2: 854
Route 2
2,028 ft
none
none
3 buildings, tallest 22 ft
Route 3
2,589 ft
none
none
1 buildings, tallest 22 ft
Route 4
2,589 ft
none
none
1 buildings, tallest 22 ft
Route 3A
2,047 ft
none
none
3 buildings, tallest 22 ft
Sources: Loudoun County LandMARC public records (FIDP-2018-0001, FIDP-2022-0002, ZCPA-2017-0007, STPL-2023-0013, EPLAN-2024-0113, EPLAN-2026-0012, EPLAN-2026-0033, permits at 22644 Amendola Ter); County GIS parcels, road edges and zoning; VBMP 2026 imagery.
County Water Bodies outlines drawn as a flat surface 0.3 m above LiDAR ground. The County leaves one stream line in this area unnamed; it runs inside the Broad Run channel outline and is labeled Broad Run.
Dominion has not published structure coordinates for Route 3A. The model puts a structure at every point of Dominion's Route 3A centerline, plus one at mid-span on each straight stretch longer than 400 m.
Why this rule is reasonable: the centerline has 78 points and the record has 74 structures; near-straight points plus the long mid-spans give 15 suspension structures, the number in the record; the typical spacing of the points (613 ft) matches the record's average spans (567 to 593 ft); and on the one Dominion/ERM sheet that shows structures, four of five (S1, S3, S4, S5) sit within 1.3 m of a centerline point. S2 is about 55 ft from the centerline on that sheet, which likely shows an earlier alignment; the model puts S2 on the centerline point.
Near-straight points get the monopole suspension structure (II.B.3.vi). Angle points get the monopole double dead-end (II.B.3.vii); the sharpest angles get the 2-pole double dead-end (II.B.3.viii), keeping whole-route totals in line with the record. S3 and S5 (marked *) are kept as 2-pole as on the sheet stretch; the rule alone gives monopoles there. With them the model has 9 two-pole structures against 7 in the record for all of Route 3A.
The 8th easement, not accepted (LVE Lot M) measured#
Parcel 122497166000, 15.15 ac (legal acreage in the County parcel record). Route 3A crosses it for 733 ft, and 1.68 ac of Dominion's Route 3A right-of-way polygon lies inside it. Route 3 does not cross it: its centerline passes 68 ft outside. A 100 ft right-of-way on Route 3 would not touch it; a 150 ft one would overlap 291 sq ft at the edge. Attachment II.A.6 of the application (map Page 3 of 5, filing 380957, PDF p100, and the supplemental map Page 3 of 5, filing 380966, PDF p30) shows a 100 ft right-of-way for Route 3 in this segment, where Routes 2, 3 and 4 share one corridor along the edge of the data center campus. The maps carry no parcel lines; the segment was matched by the shape of the routes. Routes 2 and 4 pass 68 and 68 ft outside.
The 7 easements accepted on Feb. 11, 2026 measured#
Four of the seven (LVE parcels 121285101000, 090352848000, 121301369000, 121392235000) are not yet in the County easement layer and are drawn from their County parcel outlines. The three LVE II easements are in the layer (recorded April 8, 2026).
PARID 122178940000, 16.1 ac, County open-space easement over the whole parcel (instrument 201606300040798, recorded June 30, 2016). Route 3A crosses it for 2,932 ft (6.25 ac of right-of-way); Route 3 for 1,661 ft; Route 2 for 383 ft. Routes 1, 1F, 4 and 5 do not cross it.
Parcel 122391189000, 12.7 ac. Not an easement. Route 3A crosses it for 1,116 ft; Routes 2 and 3 for 328 ft; Routes 1, 4 and 5 do not cross it.
Other County-held conservation easements measured#
50 in the model area, from the County Conservation Easements layer. All crossings are measured on County parcel and easement layers with the route lines described above.
Public datasets
Dataset
Date
Used for
USGS 3DEP LiDAR, Northern Virginia (VA_NorthernVA_1_B22)
flown 2022
Ground, tree positions and heights, house roof heights, existing tower positions and heights.
VGIN Virginia Base Mapping Program orthoimagery, most recent
2026, leaf-off, 3-inch
Ground picture in every view. The cleared right-of-way is painted as meadow and is not imagery.
Loudoun County GIS: parcels, address points, buildings, road centerlines, water bodies, streams, major power lines, school sites, subdivisions, conservation easements